| Vertical Load Carrying System | 4.5" concrete (6.5" at First Floor) over steel deck supported by steel beams and columns. Concrete walls below the first floor also support the steel frames above. |
| Lateral Force Resisting System | Distributed moment resisting frames in both directions from the first to the third stories. Concrete shear walls below the first floor along the perimeter and at the middle of the building. |
| Foundation Type | Concrete spread footing with grade beams. |
| Remarks | This hospital building was instrumented as part of the OSHPD/CSMIP Hospital Instrumentation Project. |