CESMD
Information for Strong-Motion Station
Big Sur - Hwy 1/Pfeiffer Canyon Bridge [Demolished]
CGS - CSMIP Station 47729
Earthquakes recorded by this station
 
(Station Photograph - click to enlarge)(Sensor Layout - click to see PDF File)
   
Latitude 36.2391 N
Longitude 121.7747 W
Elevation (m) 176
Site Geology Alluvium
Vs30 (m/sec) 664 (inferred)
Site Class C
Remarks/Notes Site information sources
 
No. of Spans3
Plan ShapeCurved.
Total Length316' (96.3m). Bridge spans are 98.25' (29.9m), 120' (36.6m), and 98.25' (29.9m).
Width of Deck34' (10.4m)
Construction Date1968
Instrumentation1996. 15 accelerometers on the bridge. 3 accelerometers at a free-field site.
 
Superstructure Type3-cell concrete box girder. Seat abutments with rocker bearings.
Substructure TypeCircular (6' diameter) reinforced concrete column at each pier.
Foundation TypeConcrete pile shafts support the piers. Spread footings support the abutments.
RemarksThis bridge was instrumented under an interagency agreement between Caltrans and DOC.